• District 113 is developing a five-year strategic plan to guide future decision-making.  Community involvement has been crucial as we strive for continuous improvement.  The District has utilzed a robust, inclusive process that involves parents/guardians, staff, students and community members/organizations from the very beginning.

    To ensure consistency, continuity and an unbiased perspective, all of our focus groups have been facilitated by Felicity Educational Services. The District’s goal is to complete the data collection process by the end of November to ensure adequate time for a thorough critical review of the draft document prior to finalizing and rolling out the new strategic plan in April 2017.

    A timeline of the work is included on this page.

    Stage 1. Identify and Define Vision, Mission, and Key Goals with Schools, Community

    September, October 2016

    Status

    Identify key stakeholders and groups to help define district vision and key goals: School Board, Executive Council, Leadership Team, Schools, Community Groups and Leaders, Students Completed, District approved
    Invite key stakeholders and groups to help define district vision and key goals: School Board, Executive Council, Leadership Team, Schools, Community Groups and Leaders, Students Completed, District approved
    Conduct focus group meetings key stakeholders and groups to help define district vision and key goals: School Board, Executive Council, Leadership Team, Schools, Community Groups and Leaders, Students Completed
    Conduct One on One meetings with district leadership team
    • Dr. Christopher Dignam, Superintendent
    • Dr. Thomas Koulentes, Highland Park High School Principal
    • Ms. Kathryn Anderson, Deerfield High School Principal
    • Dr. Sue Hebson, Assistant Superintendent for Curriculum and Instruction
    • Mr. Barry Bolek, Assistant Superintendent for Business and Finance
    • Directors of Communication
    Completed
    Conduct Online Survey Completed 
    Review Work to Date (Referendums, Capital Projects, Course Offerings, Change in PERA, Communications, Websites, etc.) Completed
    Review District 113 Mission, Vision, Guiding Principles Completed
    Review District 113 archival data and other reports Completed
    Review District 113 student achievement data Completed
    Review Previous District 113 Strategic Plans Completed
    Host Strategic Plan Districtwide institute day to discuss Strategic Plan status and timeline Completed
    Work with Districtwide interdisciplinary teams during institute day to engage in "Vision" and "Mission" activity and identify key value statements for the District's new Strategic Plan "Vision and Mission" Completed

     

    Stage 2. Research - Needs assessment, gap analysis, program analysis, personnel analysis, budget analysis, research, etc.

    November, December 2016

    Status

    Analyze data collected in Stage 1 Completed
    Research trends in data Completed
    Identify qualitative indicators (attitudinal data) Completed
    Perform a gap analysis, program analysis, personnel analysis, budget analysis, etc. to structure and triangulate data collected Completed
    Analyze stakeholder perceptions Completed

     

    Stage 3. Write/Modify the strategic plan

    December 2016, January 2017

    Status

    Continue to work with District 113 to create general framework for global direction and priorities for strategic plan Completed
    Continue to work with District 113 to create Mission, Vision and Core Beliefs; Create Draft Mission, Vision and Core Beliefs (Values) Completed
    Meet with Board to Review Draft Mission, Vision and Core Beliefs (Values) Completed
    Continue to work with District 113 to create specific steps that will be taken in order to accomplish goals and objectives that will be identified in strategic plan Completed

    February 2017

    Status

    Continue to work with District 113 to finalize Mission, Vision, Core Beliefs (Values) Completed
    Continue to work with District 113 to create specific steps that will be taken in order to accomplish goals and objectives that will be identified in strategic plan Completed
    Continue to work with District 113 to create implementation plans for elements outlined in strategic plan Completed
    Continue to work with District 113 to create evaluation metrics for elements outlined in strategic plan Completed
    Continue to work with District 113 to identify personnel needs and additional resources for elements outlined in strategic plan Completed
    Work with individual Departments at DHS and HPHS to identify department value statements and add input regarding key objectives and steps for success Completed
    Host Strategic Plan Districtwide institute day inservice to discuss progress, next steps, and provide opportunity for keynote speaker to discuss importance of strategic planning with all staff Completed
    Work with Districtwide interdisciplinary teams during institute day to engage in "Value Statement" activity and identify key "Social/Emotional" value statement objectives Completed

     

    Stage 4. Development of implementation recommendations

    March 2017

    Status

    Formal Strategic Plan presented to Board of Education and Community Completed

    April, May 2017

    Status

    Comprehensive timeline and work plan to accomplish goals and objectives identified in strategic plan presented to Board of Education and Community In Progress

    May, June 2017

    Status

    Communications Upcoming
    Budgeting & Staffing Upcoming
    Begin to implement new Strategic Plan Upcoming